Step 1: Drawings ready for permit
Every commercial build-out starts with sealed construction documents from an architect and engineers: floor plan, reflected ceiling plan, electrical, mechanical, plumbing and fire life-safety. Incomplete or mismatched drawings are the number one reason plan review comes back with comments, so this is the step where getting your contractor involved early pays off. Our commercial construction team reviews drawings for constructability and cost before they go in.
Step 2: Plan review
For work in unincorporated Miami-Dade, the county building department says initial plan review takes between 24 hours and 10 business days, depending on the type of permit and how complex the project is (Miami-Dade Plan Review). Each discipline reviews the plans: building, electrical, mechanical, plumbing, fire and, when needed, zoning or health.
If your project is inside a city such as Miami, Doral, Miami Beach or Coral Gables, that city’s building department runs the review and sets its own timeline, so ask your contractor which department has jurisdiction before you plan your move-in date.
Step 3: Comments and reworks
Most commercial permits get at least one round of comments. The county says rework reviews also take between 24 hours and 10 business days once corrections are submitted, and the upfront fees cover two reviews (the initial review and one rework). Extra revisions are charged rework fees per discipline. Every extra round adds time and money, which is why clean, coordinated drawings matter so much.
Step 4: Permit issued and work begins
Once every discipline approves and fees are paid, the permit is issued. Miami-Dade gives you 180 days to start work and call for inspections, and each approved inspection extends the permit another 180 days. Subsidiary permits for electrical, mechanical and plumbing are pulled and inspected separately, usually by the licensed trade contractors working under the general contractor.
Step 5: Inspections and final sign-off
Inspections follow the work: rough-ins for framing and MEP before walls close, then finals for each trade and the building. A good schedule books inspections ahead and keeps the jobsite ready, so the space can open on time.
Where commercial build-outs lose time in Miami-Dade
- Drawings that don’t match the space. Field-verify existing conditions before design is finished.
- Late landlord approvals. Many Class A buildings require landlord sign-off on drawings and contractor insurance before work starts.
- Long-lead items. Storefronts, glass partitions, HVAC units and lighting can take longer than the permit. Order them as soon as the design is locked.
- Occupied buildings. After-hours work and phasing add planning time, but keep your business running.
Recent Miami-Dade build-outs
- AvMed headquarters, Doral: a 65,000 sq ft Class A headquarters build-out.
- Brightstar, Miami: a 30,000 sq ft office renovation.
- Venture X, Doral: a 15,000 sq ft coworking build-out.
- Energizer Holdings, Miami Lakes: a 14,000 sq ft office renovation.
- Barry University, Miami Shores: a 5,000 sq ft lobby renovation in an occupied campus building.
See more on our projects page, or read about our work as a Miami commercial construction company. We also handle Broward County commercial build-outs and Palm Beach County commercial construction.
Frequently asked questions
How long does a commercial permit take in Miami-Dade?
Miami-Dade says initial plan review takes 24 hours to 10 business days, and each rework review takes another 24 hours to 10 business days. The total depends on how many rounds of comments the plans get and which building department has jurisdiction.
Who pulls the permit for a commercial build-out?